Moscow, 20 March 2025: Hydraulic 24.5 MPa tests have been successfully completed in terms of density and strength at the primary circuit systems and equipment of the Rooppur NPP power unit No. 1 which is being built in the People’s Republic of Bangladesh by the Rosatom State Corporation Engineering Division. The process included several stages, […]
The post Hydraulic pressure tests have been performed at the primary circuit systems and equipment at Rooppur NPP power unit 1 first appeared on Business News Week.